Setting up the Project Status Cube - PI View

Summary

In this article, you will learn how to set up the Principle Investigator view of the Project Status Cube in Excel.

Body

   Overview   

The Project Status Cube can be set to view data based on the Principal Investigators(PI) responsible fo the project.  This article demonstrates how to properly configure the cube to display based on PI.

   Instructions   

  1. Step 1: With the Project Status Cube open in Excel, click the New Sheet button.
  2. Step 2: A new sheet is displayed. Click the Insert tab.
  3. Step 3: The Insert menu ribbon is displayed. Click the PivotTable button.
  4. Step 4: The Create Pivot Table popup is displayed. Click to select the Use an external data source option.
  5. Step 5: Click the Choose Connection... button.
  6. Step 6: The Existing Connections popup is displayed. Click in the KK_STATUS_CUBE_CONNECTION link.
  7. Step 7: Click the Open button.
  8. Step 8: Click the OK button.
  9. Step 9: Click and drag the Project Budget Amount option in the PivotTable Fields menu to the Values box.
  10. Step 10: Click and drag the Encumbrance Amount option in the PivotTable Fields menu to the Values box.
  11. Step 11: Click and drag the Actual Amount option in the PivotTable Fields menu to the Values box.
  12. Step 12: Click and drag the Project Remaining Balance option in the PivotTable Fields menu to the Values box.
  13. Step 13: Click and drag the PM Name option in the PivotTable Fields menu to the Filters box
  14. Step 14: PM Name menu is displayed. Click the All drop-down menu.
  15. Step 15: Enter appropriate information into the PM Name search field.
  16. Step 16: The matching PM Name results are displayed. Click the appropriate PM Name to select.
  17. Step 17: Click the OK button.
  18. Step 18
    Click and drag the Project ID Descr - Activity ID Descr option in the PivotTable Fields menu to the Rows box.
  19. Step 19: Click and drag the Fund Code Descr option in the PivotTable Fields menu to the Rows box.
  20. Step 20: Click the More Fields option under ACCOUNT_GL > UGAACCTTREE in the PivotTable Fields menu.
  21. Step 21: Click and drag the GL Account ID Descr option to the Rows box.
  22. Step 22The Principal Investigator view of the Project Status Cube is now displayed. 

In this article, you will learn how to set up the Principle Investigator view of the Project Status Cube in Excel.

1. Step 1

step image

With the Project Status Cube open in Excel,

click the New Sheet button.

2. Step 2

step image

A new sheet is displayed.

Click the Insert tab.

3. Step 3

step image

The Insert menu ribbon is displayed. 

Click the PivotTable button.

4. Step 4

step image

The Create Pivot Table popup is displayed.

Click to select the Use an external data source option.

5. Step 5

step image

Click the Choose Connection...  button.

6. Step 6

step image

The Existing Connections popup is displayed.

Note: To configure the KK_CUBE_CONNECTION, visit the Updating the Connection Setting for the Budget & Project Status Cubes article.

Click in the  KK_STATUS_CUBE_CONNECTION  link.

7. Step 7

step image

Click the Open button.

8. Step 8

step image

Click the OK button.

9. Step 9

step image

A blank PivotTable is inserted. To begin setting up the view you need to select the appropriate PivotTable Fields.

Click and drag the Project Budget Amount option in the PivotTable Fields menu to the Values box.

10. Step 10

step image

The Project Budget Amount column is displayed.

Click and drag the Encumbrance Amount option in the PivotTable Fields menu to the Values box.

11. Step 11

step image

The Encumbrance Amount column is displayed.

Click and drag the Actual Amount option in the PivotTable Fields menu to the Values box.

12. Step 12

step image

The Actual Amount column is displayed.

Click and drag the Project Remaining Balance option in the PivotTable Fields menu to the Values box.

13. Step 13

step image

The Project Remaining Balance column is displayed.

Click and drag the PM Name option in the PivotTable Fields menu to the Filters box.

Note: Scroll, if necessary, to view additional options.

14. Step 14

step image

PM Name menu is displayed.

Click the All drop-down menu.

15. Step 15

step image

Enter appropriate information into the PM Name search field.

16. Step 16

step image

The matching PM Name results are displayed.

Click the appropriate PM Name to select.

Example shown here:  Wilcott,Payton (1888888) tree item.

17. Step 17

step image

Click the OK button.

18. Step 18

step image

The displayed data is updated to reflect information associated with the selected Principal Investigator.

Click and drag the Project ID Descr - Activity ID Descr option in the PivotTable Fields menu to the Rows box.

19. Step 19

step image

The Project ID Descr - Activity ID Descr column is displayed.

Click and drag the Fund Code Descr option in the PivotTable Fields menu to the Rows box.

Note:  If the Fund Code Descr option is not visible, select the More Fields option under Fund > UGAFUND.

20. Step 20

step image

The Fund Code Descr information is displayed.

Click the More Fields  option under ACCOUNT_GL > UGAACCTTREE in the PivotTable Fields menu.

21. Step 21

step image

Click and drag the GL Account ID Descr option to the Rows box.

22. Step 22

step image

The Principal Investigator view of the Project Status Cube is now displayed. 

Note: The PivotTable Fields can be hidden by selecting a cell outside the PivotTable.

 

Details

Details

Article ID: 149315
Created
Sat 9/24/22 11:10 PM
Modified
Fri 1/5/24 5:07 PM