Running the Project Status Cube

   Overview   

The Project Status Cube can be used to view budget-to-actual information at the summary or detail level. This cube will be download as an Excel spreadsheet and utilizes "pivot table" functionality.

Note: F&A (95xxxx account code for indirect costs) only posts once a month, typically in the first or second week after the calendar month end. For more information, please view the financial closing schedule HERE.

In this article, you will learn the steps to download and run the Project Status Cube in the Data Warehouse.

1. Step 1

Office of Institutional Research homepage displayed with the Operational Reports link highlighted

First, log into Office of Institutional Research

From the Office of Institutional Research homepage (https://oir.uga.edu ), click the  Operational Reports link.

2. Step 2

Central Authentication Service (CAS) page displayed with the LOGIN button highlighted

The UGA Single Sign-On page is displayed. Enter the necessary information in the Username and Password fields.

Click the Login button.

3. Step 3

Operational Reports page displayed with the Project Status link highlighted

The Operational Reports page is displayed.

Click the Project Status link.

4. Step 4

Project Status operational reports menu displayed with the Project Status Cube link highlighted

The Project Status operational reports menu is displayed.

Click the Project Status Cube link.

5. Step 5

Project Status operational reports menu displayed with the Project_Status_Cube.xlsx file link highlighted

Follow the system prompts to open the Project_Status_Cube.xlsx file in Excel.

6. Step 6

Project Status Cube displayed with the Enable Content button highlighted

The Project Status Cube is opened in Excel.

To begin working with the cube, click in the Enable Content field.

7. Step 7

Project Status Cube displayed with the Project Default View tab highlighted

To view the data, click the Project Default View tab.

8. Step 8

Project Status Cube displayed with Row Header 7 highlighted

The Project Default View is displayed.

To freeze the filters and row labels, click the appropriate row header.

Example shown here: row 7 header.

9. Step 9

Project Status Cube displayed with the View tab highlighted

Row 7 is selected. The freeze panes options are located under the View tab.

Click the View tab.

10. Step 10

Project Status Cube displayed with the Freeze Panes menu highlighted

Click the Freeze Panes button.

11. Step 11

Project Status Cube displayed with the Freeze Panes option highlighted

The Freeze Panes menu is displayed.

Click the Freeze Panes.

12. Step 12

Project Status Cube displayed with the PivotTables field highlighted

The top rows are frozen in the view.

Click any cell within the table to view the PivotTable Fields menu.

13. Step 13

Project Status Cube displayed with the All menu option highlighted

Click the PM Name drop-down menu.

14. Step 14

Project Status Cube displayed with the Search field highlighted

Enter the appropriate information into the search  field.

Example shown here: " dickens ".

15. Step 15

Project Status Cube displayed with the Dickens, Charles option highlighted

The matching results are displayed. 

Select the appropriate Principal Investigator name.

Example shown here: Dickens, Charles (1801234) item.

16. Step 16

Project Status Cube displayed with the Ok button highlighted

Click the Ok button.

17. Step 17

Project Status Cube displayed with the Project ID Descr option to and the Rows box highlighted

The data is filtered by the selected Principal Investigator name.

To view Project ID Description data, click and drag the Project ID Descr option to the Rows box.

18. Step 18

Project Status Cube displayed with the All menu option highlighted

Click the Project Activity Flag drop-down menu.

19. Step 19

Project Status Cube displayed with the All Tree item highlighted

The Project Activity Flag defines whether a project is considered active or inactive. Inactive projects are those projects that ended more than six months ago.

To expand the Project Activiy flag, click the All tree item.

20. Step 20

Project Status Cube displayed with the Active Tree Item highlighted

Click the Active tree item.

21. Step 21

Project Status Cube displayed with the Ok button highlighted

Click the OK button.

22. Step 22

Project Status Cube displayed with the $375.00 Cell highlighted

The selected value is expanded to show associated data.

To drill through for additional details, right click the appropriate cell.

Example shown here: " $375.00 " cell.

23. Step 23

Project Status Cube displayed with the KK Transactions Detail Drillthrough option highlighted

The options menu is displayed.

From the options drop-down menu, follow this navigation:

Additional Actions   >   KK Transactions Detail Drillthrough.

Click the KK Transactions Detail Drillthrough option.

24. Step 24

Project Status Cube displayed with the Column A highlighted

The KK Drill Through data for the selected cell is displayed. 

Right click the appropriate column(s) you would like to exclude from the report. 

Example shown here: hide the Fiscal Year, "A" column header.

25. Step 25

Project Status Cube displayed with the Hide link highlighted

The column options menu is displayed.

Click the Hide link.

26. Step 26

Project Status Cube displayed with Columns B,C,D,E,F highlighted

The selected column is hidden. Repeat these steps as necessary to hide columns not needed in this view.

27. Step 27

Project Status Cube displayed with Columns J,K,L highlighted

Choose the appropriate columns headers to display the Actual Amount and Encumbrance Amount data in accounting format. 

Example shown here: "J" through O" column headers.

28. Step 28

Project Status Cube displayed with the Home button highlighted

With the appropriate columns selected, click the Home tab.

29. Step 29

Project Status Cube displayed with the Accounting Number Format button highlighted

Click the Accounting Number Format button.

30. Step 30

Project Status Cube displayed with Columns H,J,K and the Project Default View button highlighted

The columns are displayed in an accounting format.

To return to the previous view, click the Project Default View tab.

31. Step 31

Project Status Cube displayed with the UGAACCTTREE option highlighted

The Project Status Cube is displayed.

To filter by specific account code information, click the [>] button before the  UGAACCTTREE option in the PivotTable Fields menu.

32. Step 32

Project Status Cube displayed with the UGAACCTTREE Level01 option highlighted

Click the + button before the UGAACCTTREE Level01 tree option.

33. Step 33

Project Status Cube displayed with the 000000 - Accounts option highlighted

The UGAACCTREE Level01 menu is displayed.

Click the [+] expansion button to the left of 000000 - Accounts option.

34. Step 34

Project Status Cube displayed with the 000000 - Accounts option highlighted

The 000000 - Accounts list is expanded.

Use the check boxes to deselect the appropriate options for removal from display. 

35. Step 35

Project Status Cube displayed with the OK button highlighted

With the appropriate options selected, click the OK button.

36. Step 36

Project Status Cube displayed with the Project View data highlighted

The selected options are removed from the report.

Additional Information: